What is SAM (SMV) and how to calculate it

Standard Allowed Minute is the base of every target, efficiency and cost in a garment factory. Here is how it is built, step by step.

2 min read · Updated 15 Sep 2026 · By Md. Saiful Islam

SAM (Standard Allowed Minute), also called SMV (Standard Minute Value), is the time a trained operator needs to complete one operation at a normal pace, including allowances for fatigue and personal needs. Almost every number an industrial engineer uses - targets, efficiency, line balancing, costing - starts from SAM.

Why SAM matters

  • Targets: how many pieces a line should make per hour.
  • Efficiency: how well the line used its available minutes.
  • Costing: labour cost per garment = SAM × cost per minute.
  • Planning: how many lines and days an order needs.

The three building blocks

SAM is built from three parts:

PartWhat it means
Observed timeThe average time you measure with a stopwatch
RatingHow fast the operator worked compared with a normal pace (100%)
AllowanceExtra time for fatigue, personal needs and small delays

Formula: Basic time = Observed time × Rating ÷ 100. SAM = Basic time × (1 + Allowance ÷ 100).

Worked example: attaching a pocket

You time an operator for 10 cycles. The average is 30 seconds (0.50 minutes). She works slightly faster than normal, so you rate her at 110%. The factory uses a 15% allowance.

  1. Basic time = 0.50 × 110 ÷ 100 = 0.55 min
  2. SAM = 0.55 × 1.15 = 0.633 min

Add the SAM of every operation in the garment and you get the garment SAM. A basic T-shirt is often around 5-8 minutes; a formal shirt may be 18-25 minutes, depending on the design.

Two ways to get SAM

  • Time study: measure real operators with a stopwatch, then apply rating and allowance (as above).
  • Predetermined time systems such as GSD: build the time from standard motion codes, without depending on one operator's speed. This gives more consistent values across factories.

Common mistakes

  • Timing too few cycles. Take at least 10 good cycles and remove abnormal ones.
  • Rating every operator at 100%. Rating is a skill; practise with training videos.
  • Forgetting machine delays and bundle handling in the allowance.
  • Using the buyer's costing SAM as the production target without checking it on the floor.

Tip: Keep one SAM per operation in your operation bulletin and reuse it everywhere, so targets, efficiency and costing all use the same number.