Solved IE exam problems: group efficiency, pitch time, throughput time and thread requirement

🔒 Members

Two real written-test problems for IE executives, solved step by step: line and group efficiency and performance, pitch time, balancing ratio, throughput time, production achievement and thread cones for an order.

3 min read · Updated 08 Oct 2026 · By Md. Saiful Islam · বাংলায় পড়ুন

Factories often give IE candidates a written test with numbers. Here are two typical problems, solved step by step. Try them yourself first, then check.

Problem 1 - four lines, one group

LineGarment SMVWorkersLeft in OTProduction (10 h)Lost time (min)Bottleneck SMV
118.65732717008000.30
219.12753116306200.33
320.55712515907850.35
417.12702218106650.28

Working day is 10 hours: 8 regular hours with all workers + 2 OT hours after some workers left.

🔒

Continue reading as a member

This lesson is for registered members. Register, pay with bKash, and get full access to all member lessons and files.

Get one practical IE tip every week

Join IE and production professionals learning with in2eff.