Most late shipments were late long before production started - a lab dip approved a week late, fabric booked after the deadline, trims arriving on the day of cutting. The Time and Action (T&A) calendar makes these dates visible from the first day.
Build it backwards
Start from the ex-factory date and subtract the lead time of each step:
| Step | Typical lead time (example) | Due day |
|---|---|---|
| Ex-factory | - | D70 |
| Final inspection | 2 days | D67-68 |
| Finishing & packing | 9 days | D58-66 |
| Sewing | 14 days | D51-64 |
| Cutting | 6 days | D48-53 |
| PP meeting | before cutting | D46 |
| Fabric dyeing, finishing, inspection | 16 days | D29-44 |
| Fabric knitting / weaving | 28 days | D1-28 |
| Lab dip approval | needed before dyeing | by D13 |
Lead times depend on your suppliers, fabric type and capacity - use your own history.