A costing sheet is a promise: if the numbers are wrong, the factory either loses the order or loses money on it. A good FOB costing is built from parts you can check.

FOB price build-up for one T-shirt
FOB price build-up for one T-shirt

The parts of an FOB price

Formula: FOB = fabric + trims + CM + washing/printing/embroidery + testing & commercial + profit (+ buying commission if any)

1. Fabric cost Fabric per dozen (kg or yards, including wastage) × price per kg/yard ÷ 12 = fabric cost per piece.

2. Trims and packing Sum of every BOM item per piece: thread, labels, hangtags, buttons, zippers, poly bag, carton share, tissue, stickers.

3. CM (cut and make)

Formula: CM per piece = SAM × cost per minute

Cost per minute = factory monthly cost (wages, overheads, utilities, depreciation) ÷ produced minutes per month at your expected efficiency.

4. Washing / printing / embroidery - from the supplier's or in-house department quote.

🔒

Continue reading as a member

This lesson is for registered members. Register, pay with bKash, and get full access to all member lessons and files.

Get one practical IE tip every week

Join IE and production professionals learning with in2eff.