Production planning in Excel: Gantt chart, working calendar, job sequencing and set-up matrix

🔒 Members

Build a real planning tool in Excel: a Gantt chart that flags late jobs, a Julian working calendar with breaks and shifts, cascading job times, re-sequencing, multiple work centres and a set-up matrix with INDIRECT.

1 min read · Updated 08 Oct 2026 · By Md. Saiful Islam · বাংলায় পড়ুন

Lessons 22-38 of the workbook build a complete scheduling tool. Here is how each piece works, so you can build your own for a sewing floor, embroidery or washing.

1. A simple Gantt chart that flags late jobs

Enter each job's hours in column C. The first job starts at 0; each next job starts when the previous one stops:

  • Start: =IF(C17>0, E16, " ")
  • Stop: =IF(C17>0, C17+D17, " ")
  • Hours left to the delivery date: =INT((E11-NOW())*10) (10 working hours a day)
  • Status: =IF(E17<=E$13, "In-time", "Late")

The chart area has hour numbers across the top and a 1 where the job runs:

=IF(H$15<=$C$36, IF(AND(H$15<=$E16, $D16<H$15), 1, " "), " ")

Conditional formatting colours 1s turquoise for in-time jobs and red for late ones. Move rows up or down to test a better sequence.

🔒

Continue reading as a member

This lesson is for registered members. Register, pay with bKash, and get full access to all member lessons and files.

Get one practical IE tip every week

Join IE and production professionals learning with in2eff.